On December 9 Pakistani local time, the Unit 1 boiler ignition and pipe blowing of Hubco 2 *660MW Coal-Fired Power Plant Project was successfully completed.
The pipe blowing, lasting four days, was performed in three stages 63 times in total. The 62nd and 63rd pipe blowings were excellent, which met the requirements of quality assessment and the client. Three targets were given, after the acceptance of targeting, totaling 66 targets.