On December 27 Pakistani local time, the admission of the 1# steam turbine of Pakistan HUBCO 2×660MW Coal Power Plant Project succeeded at the first attempt, with a fixed speed of 3000rpm and a maximum bearing vibration of 73um. The unit operated smoothly and all the indexes were excellent.
During the admission, all the staff worked orderly and cooperated closely to ensure this success, and they are moving towards the synchronization at the end of the year.