Casting of Turbine Room of Serbia Pancevo Project Initiated
 

On March 30, 2019(L-TM), TEPC Serbia Pancevo Project initiated the casting of concrete foundation of the gas turbine room.

From January 5, 2019 when the gas turbine room foundation excavation was commenced, to January 22 when the pile driving works began, to March 30, 2019 when the casting of concrete foundation of the gas turbine room was initiated, the Pancevo Project Department managed to address all kinds of challenges, including intricate operating procedure, delayed delivery of drawings and repeatedly modification of drawing due to the lack of power plant design experience of the local design institute, subcontractors’ ignorance of construction progress and indolent work style, with TEPC Spirit of taking the initiative to take the lead with an attitude of preciseness and reliability. The casting of gas turbine room concrete foundation laid a solid foundation for the following installation of steel work.