The Main Transformer Unloading of the Male Ring Network (Phase I) Project Completed
Date:2020-10-19 VisitCount: Font size:[ L M S ]
  

  On September 12, local time, the MalPes TV News Channel (CNM) reported on the MalPes Male Ring Network (Phase I) project and the project’s main transformer unloading process had been broadcast live.
  The report pointed out that the project is the largest and highest voltage substation in the Republic of MalPes. The six 132kV transformers of the three substations of the MalPes Male Island Ring Network (Phase I) project contracted by Energy China were successfully unloaded and placed in place, which marked the formal entry of the equipment installation stage of the project.
  In the face of difficulties such as the high base of the main transformer, the small space, the lack of resources, and the risk of epidemics, the project department made careful organization, advanced plan, and targeted measures. The Hulhumale station, which has the highest risk, had been lifted three times and moved three times from unloading to its position so that the potential safety hazards caused by one-time jacking was eliminated.
  The project includes three 132kV substations and 132kV and 11kV cable line projects between the substations. The project is located on Male Island, Airport Island, and Hulhumale in the Republic of MalPes. In the form of a consortium, Dongfang Electric International Corporation as the project leader, combining with the Northwest Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group contracted for the EPC project, and Energy China TEPC was the general contractor for the construction.