On November 16, local time, the initial hoisting on the steel structure of No.3 boiler of Indonesia Meulaboh coal-cired power plant project was conducted by CEEC TEPC.
It is reported that the project is located in Meulaboh County, the north of Sumatra Island, Nanggroe Aceh Darussalam, Aceh Province, Indonesia, which plans to build two sets of 225MW subcritical units, with the total installed capacity 450MW. It is the first large-scale thermal power project with a complete GC mode undertaken by CEEC TEPC in the Indonesian market. |