Protect eyesight:
Turbonator Stator Hoisted in Position, Serbia Pančevo Project
Date:2020-03-25 VisitCount: Font size:[ L M S ]
  

   At 13:50 of December 12th, local time, the turbonator stator was hoisted in place.
  The turbonator stator used within Pančevo Project was manufactured by power plant of Shanghai Electric Power Generation Group Co., Ltd. The size of stator was 9500mm×3476mm×3600mm. The lifting weight was 135t. The stator was in its position on the steam turbine operation platform within steam-turbine house, with elevation of 9.5m. A 350T crawler crane was used for stator hoisting.
  In order to ensure the successful completion of the lifting task, the project department made a detailed lifting plan. The supervisor, the owner and the project leader participated in the safety and technology disclosure to the personnel taking part in the hoisting task.
  The turbonator stator was hoisted in place smoothly, which marked that the main body installation work of steam turbine would about to be fully launched.

print】【close
Prev:
Next:

     
Produced By 大汉网络 大汉版通发布系统