Generator Stator of the Second Unit Hoisted in Position, Dubai Hassyan Project
Date:2020-03-25 VisitCount: Font size:[ L M S ]
  

  On December 11th, the generator stator of the second unit in Dubai Hassyan Project was successfully hoisted in position on its first trial.
  Since November 24th, 2019, to ensure the smooth progress of the project, the engineering project department of Dubai Hassyan project spent 18 days on hoisting high-pressure heater HP6 (117T), HP8 (141T), HP7 (153T), HP6 BIS (74T), and the deaerator of unit No. 1 (154T) in positions, etc.; From December 1st to 3rd, 2019, the Tube Bundle modules (130T) of 4 condensers was hoisted in positions.
  On December 11th, 2019, the generator stator (397T) was hoisted in position. During this period, the high-pressure cylinder module (78T), intermediate pressure cylinder module (117T), the generator rotor (97T), and the low-pressure outer cylinder of unit No.2 were also hoisted and stored at the platform of operation floor within steam-turbine house.
  The major hoisting work within main power house of the unit No.2 was finished.