Missan Combined Cycle Power Plant Project department completed the foundation pouring work of the gas turbine base and the main transformer
Date:2020-03-25 VisitCount: Font size:[ L M S ]
  

  Through delicate planning and organization, Missan Combined Cycle Power Plant Project department completed the foundation pouring work of the gas turbine base and the main transformer in a continuous 24 hours.
  From 8:24 P.M. on March 12, 2020, local time in Iraq to 3:00 A.M. the next day, the project department organized the completion of the first-phase bottom plate pouring work for #1 gas turbine base. Since the foundation construction started, the project management patiently provided guidance and real-time deployment of resources to ensure the steady progress of project in respect of safety, quality and progress under the pressure of epidemic threats, lack of staff, and time shortage. The client, general contractor and the project managers tracked the whole progress of the project, praised the diligence of the employees present, and approved the rapid and effective progress.
  In the afternoon of March 13, the foundation of #1 gas turbine main transformer was completed. The management of the project department worked continuously and reduced the rest time. The construction acceptance and pouring work were completed at one time.
  Coincidently it is the first anniversary of the project’s entry, the settlement of two important milestones will undoubtedly make the best summary of the efforts of the past year. Recalling the hardships, we realize that the difficulties will always be there, but we are more convinced that the hardship are only temporary, and our determination and confidence will definitely push the project forward. Employees in Missan Project are ready to march towards the goals at all levels.