Two Milestones Completed in One Day-- CEEC TEPC Iraq Missan Combined Cycle Power Plant Project
Date:2020-05-06 VisitCount: Font size:[ L M S ]
  

  On April 30, two major milestones- SS hoisting for GT house and concrete pouring of GTG base plate- were completed for the Iraq Missan Combined Cycle Power Plant project, designed by CEEC ZEPDI and contracted by TEPC.
  Difficulties in manpower, machinery and materials shortages were overcome by all in the project office so that 13 team workers and 5 management worked over night for six and half hours casting 190 cubic meters of concrete. On the same day, the SS hoisting team had completed the hoisting of main framework for Unit 1 GTG powerhouse.
  The successful completion of these two milestones have created favorable conditions for the upcoming GT positioning work.