Stack Erected by TEPC in Pakistan Jamshoro Project
Date:2020-08-17 VisitCount: Font size:[ L M S ]
  

  On 2nd August, the Construction of the Stack by Energy China Tianjin Electric Power Construction in Pakistan Jamshoro 2×660 MW Ultra-Super Critical Thermal Power Plant Project was successfully completed, 18 days earlier than what was scheduled.
  Unlike the former gradually graded ones, this stack stands 210 metres high, with the thickness of its reinforced concrete outer cylindrical wall up to 460 mm and each customized steel formwork concrete up to 47 m3. The higher the cylindrical wall reaches, the more difficult it is to pour the concrete. However, all difficulties have been overcome by the project department engineers. The stack was successfully erected owning to their innovation by adopting electrical lift molding method and multi-functional elevator SC200/200.