Concrete Pouring of No. 1 Water Tank Completed by TEPC in Missan Project
Date:2020-08-17 VisitCount: Font size:[ L M S ]
  

  On 31st July, mass foundation concrete pouring of the No. 1 comprehensive water tank was completed by Energy China TEPC in Missan Combined Cycle Power Plant Project. The pouring lasted 9 hours and 40 minutes, with a total pouring volume of 522m3.
  In spite of the torrid heat, strict curfew, and aging equipment, among many other problems, the whole pouring was coherent and well-organized, and the concrete temperature was well-controlled due to the effective arrangement.
  Problems such as personnel and material shortage brought about by the Covid-19 pandemic has been overcome through dedicate plan to ensure the consistent performance of the project, which laid a good foundation for the next installation process.