Foundation Concrete Pouring Completion of 2# Unit for Pakistan Bin Qasim Project Contracted by ENERGY CHINA TEPC
Date:2021-01-15 VisitCount: Font size:[ L M S ]
  

  On December 25th local time, the foundation concrete pouring of 2# unit for Pakistan Bin Qasim third stage of project contracted by ENERGY CHINA TEPC Has completed.
  The project is located in Qasim Port, Karachi, Pakistan. The power plant uses liquefied natural gas as the main fuel and light diesel as the auxiliary fuel. It plans to adopt two sets of 4000F-class One-on-one single-shaft combined cycle arrangements. Tianjin Electric Power Construction Co., Ltd. is mainly responsible for on-site temporary construction, plant-wide installation and contracting of the main plant construction project.